Powering Up a System with the Linux OS and SGI Management Center Installed
Use the following procedure to power up a system that has the Linux OS installed and was factory integrated with the
SGI Management Center cluster management software:
1. Verify that the power cords are connected to the rear of the system and the site power source.
2. Move the system enable switch on the rear of the enclosure to the ON position
Note:
The system enable switch applies power to all internal trays and switches. The headnode (located in the top
tray) is the only node that is configured to power-on automatically. The compute nodes do not power-on automatically;
you must start them manually with the cluster manager or
ipmitool
command.
3. Power up the compute nodes using the cluster management software or the
ipmitool
command:
To use the SGI Management Console graphical user interface, refer to the SGI Management Center System
Administrator's Guide, publication number 007-5642-00x.
To use the SGI Management Console command-line interface, enter the following command from the headnode:
powerman -1 -n [n001-00X]
For example, the following command powers up nodes 001 through 005:
powerman -1 -n [n001-005]
To use
ipmitool
, enter the following command for each compute node from the headnode:
ipmitool -I lanplus -H [node_bmc_ipaddr] -U admin -P admin power on
For example, the following command powers up compute node 1:
ipmitool -I lanplus -H 10.0.40.1-U admin -P admin power on
4. Change the headnode hostname and IP address to the desired settings for your site, and change the headnode BMC IP
address to the desired setting for your site. Refer to the SGI Management Center Quick Start Guide, P/N